DS-174 Irrigation Pipeline Project

Description of Work: Construction of 5.645,00-mt (GRP) Main Irrigation Pipeline Project at Jebel Ali (Line7) and Al Ain Road (Line-5) Sections for Dubai Municipality (DEWA)

Project Comprising of

  • Supply Machine & Equipments, Installations, Montages, Testings
  • Deep Exc. of Trench Depths up to -10,50 mt with Open-Cut Methods
  • GRP Pipes, Fittings, Gravels, Geotextiles supplied by client 
  • ...

Total Contract Value   : 9.525.254,00 -AED
Main Contractor   : GURIS & AJD LLC JV.
Location   : Dubai / UNITED ARAB EMIRATES
Completed Date   : 2009

Share

DS-174- DEWA IRRIGATION PIPELINE PROJECT (DUBAI)

Description of Work: Construction of 5.645,00-mt (GRP) Main Irrigation Pipeline Project at Jebel Ali (Line7) and Al Ain Road (Line-5) Sections for Dubai Municipality (DEWA)

Project Comprising of

  • Supply Machine & Equipments, Installations, Montages, Testings
  • Deep Exc. of Trench Depths up to -10,50 mt with Open-Cut Methods
  • GRP Pipes, Fittings, Gravels, Geotextiles supplied by client 
  • Re-bars, Concretes, PVC Membrans, etc. supplied by client
  • Const.&Inst. of Ø500mm GRP Pipeline/Fittings: 975,00 mt
  • Const.&Inst. of Ø800mm GRP Pipeline/Fittings: 2.030,00 mt
  • Const.&Inst. of Ø1000mm GRP Pipeline/Fittings: 2.640,00 mt
  • Inst.of De-watering (Wellpoint Sys) Inc. Lagoons : 6.220,00 mt
  • Construction of Cast-in-situ Chambers (diff. types): 29,00 Nos
  • Inst. of GRP Fittings (Elbows,Tee,Y branchs, Reducers, Nozzles) 
  • Inst. of Scada Cables for to control and monitoring the network
  • Inst. of Washout, Air Walve, Tee Connections (inc. fittings)
  • Providing Initial Survey Team to access site condition
  • Restoration of all areas disturbed by the works

Total Contract Value : 9.525.254,00 -AED
Main Contractor : GURIS & AJD LLC JV.
Location : Dubai / UNITED ARAB EMIRATES
Completed Date : 2009