‘K.Cekmece-Florya’ Sewerage Project (İski̇)

Description of Work: Installation of 3.870,00 mt. Sewerage Pipeline Main Collector of (Including RCP Lake Crossings ) “Kücükcekmece to Florya Region at Istanbul City”

Project Comprising of 

  • Supply Plant&Equipments, Installation, Testing 
  • Const.&Install of Ø1800mm Reinforced Concrete Pipes
  • Const.&Install. of Precast and Cast-insitu Manholes: 37 Nos
  • ...

Total Contract Value   : 5.541.372,00 -USD 
Client   : İSKİ (Istanbul Water&Sewerage Adm.)
Location   : Istanbul / TURKEY
Completed Date   : 1994 

Share

‘K.CEKMECE-FLORYA’ SEWERAGE PROJECT (İSKİ)

Description of Work: Installation of 3.870,00 mt. Sewerage Pipeline Main Collector of (Including RCP Lake Crossings ) “Kücükcekmece to Florya Region at Istanbul City”

Project Comprising of 

  • Supply Plant&Equipments, Installation, Testing 
  • Const.&Install of Ø1800mm Reinforced Concrete Pipes
  • Const.&Install. of Precast and Cast-insitu Manholes: 37 Nos
  • Sheet Pilings (up to 12,00mt): 61.920,00 m²
  • Fabrication & Manufacturing of Concrete and RCP Pipes
  • Fabrication & Manufacturing of Precast Concrete Manholes 
  • Providing Initial Survey Team to access site condition
  • Restoration of all areas disturbed by the works
  • RCP supplied by Client (ISKI)

Total Contract Value : 5.541.372,00 -USD
Client : İSKİ (Istanbul Water&Sewerage Adm.)
Location : Istanbul / TURKEY
Completed Date : 1994