‘RIVER CROSSING BRIDGE’ CONSTRUCTION PRJ.

Description of Work: Construction of River Crossing Bridge at Tuzla (Asian Side) on Marmaray CR3 Railways Contracts.

Project Comprising of

  • Supply Plants&Equipments, Installation, Testing
  • Excavation: 2.611 m³, Backfilling with PMT: 255 m³
  • Installation of C30 Concrete Castings : 5.183 m ³
  • ...

Total Contract Value : 606.832,74 - EURO
Client : Obrascon Huarte & Siemens J.V
Location : Istanbul / TURKEY
Completed : 2015

Share

‘RIVER CROSSING BRIDGE’ CONSTRUCTION PRJ.

Description of Work: Construction of River Crossing Bridge at Tuzla (Asian Side) on Marmaray CR3 Railways Contracts.

Project Comprising of

  • Supply Plants&Equipments, Installation, Testing
  • Excavation: 2.611 m³, Backfilling with PMT: 255 m³
  • Installation of C30 Concrete Castings : 5.183 m ³
  • Installation of Re-bars (Ø8-Ø32mm) : 1.233 Ton
  • Installation of Doka Formwork Sytems: 8.244 m²
  • Installation of Scaffolding: 2.116,37 m³
  • Installation of Prizma(1x50mm) NYY Cable: 139,10 m²
  • Inst. of Galvanized Strip (with Bransman Bolts): 500,22 mt
  • Drilling Conc. Surfaces,Epoxy Anchorings(30cm): 1.293 Nos
  • Installation of PVC Water Stoppers: 694,16 mt
  • C40 Concrete, Re-bars provided by Client (Labour Cost Contract)

Total Contract Value : 606.832,74 - EURO
Client : Obrascon Huarte & Siemens J.V
Location : Istanbul / TURKEY
Completed : 2015