Eurasia Tunnel Infrastructure Projects

Description of Work: Infrastructure Displacement (9.720-mt) and Drainage Works of D100 (E5) & Side Roads between Koşuyolu Junction and Göztepe Bridge, Infrastructure Works of OCC Buildings on Istanbul Strait Road Tube Crossing Project.

Project Comprising of

  • Supply Plants&Equipments, Installation, Testing
  • Concrete-Asphalt cuttings, Manhole Shaft Elevations on Road
  • Const.&Inst. of Ø300-Ø600mm Int. Concrete Pipes: 5.720,00 mt
  • ...

Total Contract Value   : 5.275.960,00 -TL (2016 Unit Price) 
Client   : Yapı Merkezi & SK Eng. J.V
Location   : Istanbul / TURKEY
Completed Date   : 2017

Share

‘EURASIA TUBE TUNNEL’ INFRASTRUCTURE PROJECTS
(World’s First Two-Deck Highway Tunnel Under The Seabed) 

Description of Work: Infrastructure Displacement (9.720-mt) and Drainage Works of D100 (E5) & Side Roads between Koşuyolu Junction and Göztepe Bridge, Infrastructure Works of OCC Buildings on Istanbul Strait Road Tube Crossing Project.

Project Comprising of

  • Supply Plants&Equipments, Installation, Testing
  • Concrete-Asphalt cuttings, Manhole Shaft Elevations on Road
  • Const.&Inst. of Ø300-Ø600mm Int. Concrete Pipes: 5.720,00 mt
  • Const.&Inst. of Ø800,1000,1200mm Int. RCP Pipes: 2.133,00 mt
  • Const&Inst. of Ø200,300,400 mm HDPE Filter Pipes: 1.135,00 mt  
  • Const&Inst. of Ø75,100,125,160,200 mm U-Pvc Pipes: 732,00
  • Inst. of P/C Manholes (Gully Base, Rings, Conics): 98 Nos
  • Installation Cast Iron Drainage Duct Gratings (400kN,39Kg/Nos)
  • Sheet Pilings: 6.621,00m², Trench Drag Boxes/Verbau: 9.435,00 m², 
  • Monitoring Installed Pipes (8.538,0-mt) by Robot and CD Recordings                                
  • Providing initial Survey Team to access site condition
  • Restoration of all areas disturbed by the works

Total Contract Value : 5.275.960,00 -TL (2016 Unit Price) 
Client : Yapı Merkezi & SK Eng. J.V
Location : Istanbul / TURKEY
Completed Date : 2017