Description of Work: 23.800,00-m³ Deep Excavation (up to -26,90 mt depth from GL) Lifting soils to Ground Level and shifting to approved damping area at Sirkeci North&South Entrance (Tube Station & Ventilation Shafts) for Marmaray BC1 Projects.
Project Comprising of
Total Contract Value : 528.981,050 -USD
Employer : DLH (Gen. Directorate of Construction)
Main Contractor : Gama & Nurol & Taisie J.V
Location : Istanbul / TURKEY
Completed Date : 2012
VENTILATION SHAFTS, DEEP EXCAVATION & SHORING PRJ.
Description of Work: 23.800,00-m³ Deep Excavation (up to -26,90 mt depth from GL) Lifting soils to Ground Level and shifting to approved damping area at Sirkeci North&South Entrance (Tube Station & Ventilation Shafts) for Marmaray BC1 Projects.
Project Comprising of
Total Contract Value : 528.981,050 -USD
Employer : DLH (Gen. Directorate of Construction)
Main Contractor : Gama & Nurol & Taisie J.V
Location : Istanbul / TURKEY
Completed Date : 2012